The Station Oxley
Client : Heathley REIT
System Size : 99.9kW w/ provisions for extra 120kWp
Approximate Yearly Output : 152,000kWh
Solar Bay were engaged to install a 297kW system behind the gate meter that feed into the landlords existing embedded network.
Planning & Consultation
At the early stages of development, the planning process included understanding the goals of the REIT’s management. A turn-key solution that would decrease the tenants overall energy cost using renewables was the objective. As this was a Greenfield build, there needed to be consultation with the architects and builders to allow appropriate room for all of the equipment.
Engineering & Installation
Future proofing the buildings energy system was one of the main priorities. In doing so, we engineered extra breakers and cabling to allow for expansion and batteries in the future. We liaised with the onsite builders and installed along the construction roadmap.
Paperwork & Administration
When dealing with Embedded Networks and solar systems, it is extremely important to understand the regulations, exemptions, council permits and grid connection approvals needed before and after installation.
Commissioning & Onboarding
Every network has different policies that need to be followed when commissioning a large scale solar system and internal main switchboard. Proper sign-off’s were required before commissioning. There is a strong emphasis on education around why the energy is cheaper on sites that have an embedded network and solar system, so the onboarding process is extremely smooth and transparent.
Safety
Safety was taken into consideration from the first site visit. All measures were put in place for OHS, working at heights, toolbox talks, SWMS and electrical safety.