100kWp BBC Plastics Commercial Solar

Client :BBC Plastics

Tags :commercial solar

System Size : 100kWp

Approximate Yearly Output :139,000kWh


BBC Plastics partner with Solar Bay to support sustainability.

BBC Plastics Overview

icon-occupier-3

BBC Plastics have a significant load, so the main goal was to maximise their roof space.

options[1]

Shade creates a minor impact on solar system.

icon-occupiers-2[1]

100% self consumption creates a faster payback.

item-occupiers-1[1]

Minimal maintenance or management costs.

The Challenge

This was a simple straightforward industrial installation. CT clamps had to be installed on bus bars for consumption data which could only be done on shut down on the plant and equipment, which is a major operation in a 24/7 operation. Completed successfully and without any inconvenience to the business.

The Equipment

3 x Fronius Eco 27 Inverter

allmax

Trina Honey 275watt panels

Production - Daily

The Process

01
Site Visit

During the initial site visit Solar Bay collects information on the existing electricity contracts, roof weight bearing and generation capacity, buildings electricity consumption profile, and most importantly the client goals.

02
Analysis

Energy interval data and network tariff analysis showed a 60kW system would reduce total grid energy consumption to a new threshold allowing for a network tariff change, while only resulting in minimal export.

03
Grid Connection Application

Grid connection was a straight forward process, grid protection was required, as expected.

04
Structural Engineering Certificate

Due to internal cranes at the site the load bearing capacity of the roof was not a limiting factor of the install.

05
System Design

Two Fronius 27kW inverters each with five strings were designed to maximise performance, at minimal cost.

06
Safety

Safety was taken into consideration from the first site visit. All measures were put in place for OHS, working at heights and electrical safety.

07
Installation

After identifying the location for the inverters and cabling, the team worked for 10 days to install the system.

08
Handover

A detailed handover and instruction manual was provided to Radcoflex to ensure all of their questions could be answered.

Related Projects

Radcoflex Australia

Radcoflex Australia

A 60kW system reduced energy costs and allowed for a network tariff change.

View Project

Hartex Engineering

Hartex Engineering

A significant investment was made back into the company for future competitiveness.

View Project

BBC Plastics

BBC Plastics

100% self consumption 100kWp solar system.

View Project
×
  • Download our free guide to
    power purchase agreements 7 things you must know when dealing with PPA

×
  • Download our free guide to
    power purchase agreements 7 things you must know when dealing with PPA