McHugh Engineering Commercial Solar

McHugh Engineering and Solar Bay partner to drive down electricity expenditure with a Commercial Solar Solution.

01

Mchugh Engineering Solar

Overview

icon-occupier 3

99kW PV Commercal Solar System installed to reduce reliance on the grid.

options

Average yearly electricity spend was $20,800

icon-occupiers 2

Expected new yearly spend close to zero, after revenue from electricity exported.

item-occupiers 1

Future proofing the business and ready for battery install when commercially feasible.

The Challenge

Energy reliability and reducing cost was Les Mchugh’s two goals for looking into solar. With the cost of energy increasing, it makes operating a manufacturing company more difficult within Australian borders. Les trusted Solar Bay to provide the best energy solution. A 303 panel, eight tonne commercial solar system was installed, and a backup diesel generator was explored.

Production - Daily

02

The

Equipment

Fronius Inverters

trinatallmax02

Trina 330 watt panels

grid-preotection-box

Grid Protection Unit

Project Goals

Significantly reduce the electricity cost by installing a battery ready commercial solar system with minimal business interruptions.

03

The

Process

  • 01

    Site Visit

    During the initial site visit Solar Bay collects information on the existing electricity contracts, roof weight bearing and generation capacity, buildings electricity consumption profile, and most importantly the client goals.

  • 02

    Analysis

    As only an accumulation meter was installed Solar Bay installed a temporary energy meter that recorded energy usage every 30 seconds. Data analysis showed that the business had a energy consumption profile well suited for solar. As the client goal was to increase energy independence the system was sized up the maximum eligible for the upfront subsidy, 99kW. As the system will export significant amount of energy an energy plan was selected that maximised revenue, at a future date a battery system will be connected to store this energy, resulting in a highly energy independent business.

  • 03

    Grid Connection Application

    With a sub-station located directly behind the Main Switch Board the grid application process was straight forward.

  • 04

    Structural Engineering Certificate

    A structural assessment was completed and the results allowed for flexible panel placement, the north facing roof was selected to maximise generation.

  • 05

    System Design

    Three Fronius 27kW inverters were each wired with 33kW of solar modules, the Switchboard location allowed for a straightforward wiring run and install.

  • 06

    Safety

    Safety was taken into consideration from the first site visit. All measures were put in place for OHS, working at heights and electrical safety.

  • 07

    Installation

    After identifying the location for the inverters and cabling, the team worked for two weeks to install the system.

  • 08

    Handover

    A detailed handover and instruction manual was provided to McHugh Engineering to ensure all of their questions could be answered.

04

What can we do

for you

If you would like to see if we can provide you similar results please complete the form below and one of our consultants will be in touch shortly.